How can a smooth transition from the project phase to the productive phase be achieved?
Key Points
Fast-track plant builds only create value when the handover enables on-time time-to-market and rapid ramp-up to 100% capacity, that’s what turns CAPEX delivery into Operational Excellence (OPEX).
Most delays come from late operator involvement, siloed workstreams, lost know-how, and missing cross-functional processes – fixing the transition lowers Total Cost of Ownership (TCO) and prevents costly start-up losses (e.g., faulty batches, delayed commercial production).
Successful commissioning transitions follow three blocks: (1) scope & framework, (2) rollout with daily workstream choreography + automated reporting + rolling planning, and (3) critical-path management, continuous improvement, and change/team-building.
Introduction
Investments in the construction or expansion of production facilities (capital expenditure or CAPEX projects) are increasingly characterized by time and resource constraints. So-called fast-track projects are no longer the exception but have become the rule. However, in addition to the timely handover of a fully functional plant, a number of additional factors are crucial to achieving the planned time-to-market and utilizing 100% of the planned plant capacity. Only when this has been achieved can the operator speak of true operational excellence (OPEX).
The same patterns regularly emerge before and during the crucial transition to operation. The CAPEX team is entirely focused on completing the plant, while preparations for future operation take a back seat. The various disciplines, such as production, quality, or engineering, carry out a multitude of parallel activities with little coordination. Decisions are made solely on a functional basis and are characterized by short-term actionism. Know-how relating to plant data, systems, and processes is lost unused when the CAPEX team is disbanded. Future cross-functional work, both in terms of production processes and interpersonal interaction, is not recognized as critical.
Experience shows that these anomalies in the transition to productive operation can be traced back to similar areas of error, which must be identified and subsequently avoided. The future operator team is usually involved too late. At the same time, the CAPEX team and the future operators are completely disconnected from each other. Both of these factors delay the accumulation of knowledge. As a rule, there is no overall view of all the issues to be addressed, including the necessary activities and their interdependencies. There are no clear framework conditions or rules for the interaction of the individual work areas during commissioning. Clear cross-functional processes for future operation are not developed but remain confined to silos. Those involved in the process are largely unfamiliar with each other and the respective requirements of the upstream process steps and only begin to form an effective unit during the first few months of the production phase.
In addition to timely completion and 100% utilization of plant capacity, minimizing the total cost of ownership [1] (Fig. 1) – in this case, all costs incurred until planned full operation – must be a priority. In particular, the costs of initial faulty batches or the delayed start of commercial production have a significant negative impact on sales and earnings. However, these can be avoided through targeted, timely action and consideration of the key factors. An initial investment in a transformation program helps to prevent additional costs and time requirements from arising in the first place and makes the plant’s potential usable early on with market production according to plan.
Success factors
Companies that successfully manage such commissioning initiatives divide the process into three critical parts. In the first part (scope and framework), the overall scope and organizational framework conditions are defined. This includes creating a complete overview of all relevant transition elements, designing agile project management, and creating a centrally administered project plan. In the second part (rollout), the daily workstream choreography is implemented, automated reporting is launched, and a rolling planning and reporting cycle is established. Part three (monitoring and continuous improvement) comprises the active, forward-looking management of the critical path, the immediate optimization of the newly implemented processes after the initial run, and finally the rollout of the accompanying change and team-building measures.
Scope and framework
1 Transition elements
When transitioning from CAPEX to OPEX, there are a number of factors to consider first, and their existence and inclusion in the planning must be checked. The creation of the overall catalog on the basis of which the transition project plan is drawn up is at the forefront of these considerations. Some of the key issues that must be considered include operations, automation, validation, regulatory affairs, logistics, maintenance, personnel, and continuous improvement.
The topic of operations highlights all operational issues relating to the (bio)chemical process itself, clean rooms, air locks, media, HVAC (heating/ventilation/air conditioning), etc. This is complemented by the topic of automation, with questions relating to parameterization, formulation, the link to the MES (manufacturing execution system), the data landscape, and its use. Validation is usually covered in a sound manner in terms of planning during commissioning, but the elements of process, cleaning, and method validation, their documentation, and the definition of future responsibilities are not always taken into account in a timely manner and with the necessary level of detail. The same applies to all operational regulatory matters with the relevant regulations, the necessary GMP standards, and their documentation. Logistics primarily covers the entire area of material provision, flow, transfer, and storage, as well as sample management. The topic of maintenance is particularly important with regard to plant documentation, qualification, calibration, preventive maintenance, and issues of redundancy of plant components. Ensuring that personnel resources are available in good time is another essential part of commissioning. Aspects such as the necessary organizational structure, including the number of employees, the required skills (e.g., represented in a competency matrix), the personnel ramp-up curve, training planning, and the future shift model are fundamental success factors that are very often incorporated into planning too late. Last but not least, the topic of continuous improvement must be considered during the planning stage. This begins with ensuring that the lessons learned from the first batch runs are recorded and integrated – which, based on experience, has an immense influence on the rapid achievement of the planned plant capacity – and continues with the definition of key KPIs and the establishment of the future monitoring and reporting system.
Depending on when the overall catalog is created, which often happens only when the transition to operation is already underway, a review is conducted to determine which issues have already been taken into account and where gaps need to be closed. Overall, this results in a complete overview for planning the ramp-up of the plant.
2 Agile project steering
Complex transition projects require project management that guarantees a comprehensive overview of all necessary project information, provides the necessary decision-making structures, and at the same time makes the most efficient use of the resources available for project administration.
In this context, the principles of agile project management [2] have become increasingly prevalent in recent years. This aims to achieve maximum flexibility and responsiveness in order to be able to react quickly and purposefully to changes in the project. Special attention is paid to short-cycle iterative planning, ongoing update meetings (so-called stand-ups), clear prioritization of customer requirements, continuous improvement of project execution, and close risk management.
In addition to these basic principles, agile project management requires a framework for organizational support. The program organization essentially has three functions. First, it supports the processing of all relevant work packages. To this end, a subdivision into thematic work streams has proven successful. These must also be networked with each other in order to coordinate cross-cutting issues and align content dependencies. Based on the work streams, a lean management structure is needed to fulfill the second essential function. It makes the necessary decisions that cannot be made within the operational work streams. This primarily concerns strategic program management with regard to the budget, content priorities, and resource allocation. Third, the structure ensures a continuous flow of information from the shop floor to management and vice versa. The program structure is additionally supported by clearly defined roles and responsibilities for each organizational element, by a clear description and mode of operation for each type of meeting, and by a standardized program management process that maps the regular interaction of coordination and decision-making meetings.
3 Networked planning
Although the need for networked planning sounds like common sense, it is a major stumbling block in many CAPEX projects. The various program functions plan independently and without coordination, with the result that dependencies are not taken into account and lead to uncontrolled program extensions.
The basis for successful planning is the connection of all workstream tasks in a single planning source. This ensures that dependencies between individual work packages are clearly documented and, above all, that changes and their effects on the overall plan are immediately visible. As a rule, a web-based planning tool is used that combines the advantages of universal access with low costs, easy customization, and status reports at the touch of a button. Another must is defining who is allowed to make changes to the plan and under what conditions. The ability to independently change completion dates is one of the biggest pitfalls on the path to timely program completion.
Vertical and horizontal integration are hallmarks of well-networked planning. Vertical integration requires breaking down the program goals into individual work streams, defining the central work stream work packages with milestones, and deriving the necessary shop floor activities from this. The horizontal connection of work stream planning involves not only defining the dependencies between work packages but also standardizing work packages that occur in the same way in several work streams.
Roll-out
1 Daily workstream choreography
The core of the program is the completion of defined work packages within the work streams. To ensure that this is done as efficiently as possible, regular update meetings, also known as stand-ups, have proven to be effective. Representatives from various functions (e.g., operators, engineering, suppliers) meet to coordinate the daily workload. Depending on the criticality of the phase, these updates take place once or twice a day. These meetings are visually supported by so-called kanbans. These are cards on which individual activities derived from the work packages of the program plan are recorded and made visible to everyone on team boards. Kanbans and team boards are organizational tools from the world of lean manufacturing and have also proven themselves for this type of use.
During the kick-off meeting, the activities for the day are planned. This is based in particular on an evaluation of the resources actually available and any necessary short-term reprioritizations. The end-of-day meeting takes stock of planned and completed activities, and the following workday is planned in advance. This apparent additional effort is justified by the gain in transparency regarding the operational progress of the program and by an immense acceleration of the response time in the event of deviations. After a short start-up period, the teams manage to limit the meeting duration to 15-20 minutes.
2 Automated reporting
Reporting is, of course, an essential function of program management and the basis for qualified decision-making on the path to OPEX. However, experience shows that reporting is often developed as an afterthought and rarely planned strategically. This leads to inefficiencies and additional work, not only at the beginning but throughout the entire program. Reporting should therefore be as informative as necessary, but as lean as possible and automated to the greatest extent possible. The aforementioned web-based tool is an indispensable basis for this as the sole source of planning.
Above all, cleanly set up reporting requires a precise definition of the reporting parameters or KPIs. Critical questioning of the purpose of each individual key figure initially desired is indispensable in order to minimize effort. This creates a consistent KPI structure with meaningful milestones, uniform trend analyses, and similar completion dates. For each key figure, the process from data generation to the actual report, including the appropriate type of visualization, must be defined in advance. Only then can considerations for automating report generation come into play. In some cases, the use of standard software (e.g., Power BI) is sufficient, but for larger and more complex processes, Python coding is increasingly being used for the interface from the database to visualization. Although this tool requires programming expertise, it enables a high degree of requirement-specific adaptation of reporting and extensive automation.
3 Rolling planning and reporting cycle
In addition to the defined daily interaction between the various disciplines in the work streams and the framework conditions created in advance for the greatest possible automation of reporting, a clearly defined rhythm for both planning and reporting has proven its worth. This results in clear advantages for everyone involved in the program. On the one hand, decision-makers know when they are required to provide input for program management and make necessary (planning) decisions; on the other hand, they gain certainty thanks to the predefined timing of status updates. The operational program participants, in turn, know when they have to provide status updates, but also when they can expect necessary decisions and course corrections. This simplifies the separation of the effort required for formal reporting from day-to-day operational program business, avoids unnecessary reporting effort, and increases overall predictability. The frequency of planning and reporting cycles depends on the type and size of the program and, above all, on the stage the program is at. During critical program phases, such as the final stages of commissioning, qualification, or before process performance qualification (PPQ), a tighter cycle is usually established for reasons of responsiveness. During less critical project phases, the cycles can be broader in order to keep the administrative program effort as low as possible.
Monitoring and continuous improvement
1 Managing the critical path
Once the organizational measures described above (i.e., the program framework) have been implemented and the operational processing of work packages has become part of the daily routine, regular monitoring and reporting also begins. An important factor here is the management of the critical path, which determines the shortest possible program duration. This plays a central role in both retrospective and prospective assessments of the program status. In a purely retrospective status analysis, the initial focus is on whether the reported progress in processing the work packages has an impact on the desired end date or not. However, forward-looking analysis of possible deviations from the program plan and their influence on the critical path and the end date is becoming increasingly important. Various types of statistical probability analyses based on data from the central program plan are helpful here.
2 Optimization of the newly implemented processes
Throughout the entire start-up process, there are operational processes that occur repeatedly within individual workstreams or across multiple workstreams, or whose content is repeated. This is precisely where enormous potential for efficiency lies. One aspect of this is the consistent standardization of similar work packages and their elements. Such work packages (e.g., with test points that are always the same) should be identified as early as possible, defined as optimally as possible, and rolled out across all relevant workstreams. The second starting point for maximizing efficiency lies in improving activities that always run the same way immediately after the respective first runs (e.g., how to perform a specific test). Targeted process improvement and so-called lessons learned workshops help to identify extra work and errors and eliminate them for future runs. Target processes defined on the basis of these findings can then be easily multiplied through training. In addition, repetition improves routine, significantly increasing processing speed without compromising quality. These optimization measures are usually supported by a small dedicated OPEX team that has both the necessary methodological background and the required moderation skills. This allows workstream resources to be conserved for their core tasks. Overall, these measures to increase efficiency in processing could be seen as additional effort and, above all, a loss of time. However, it has become clear, especially in large CAPEX programs, that this additional investment in time and staff more than pays for itself over the entire program period.
3 Change and team-building measures
The topic of change management in projects fills countless books and its application is highly dependent on the specifics of the program. For this reason, only a few key aspects that have repeatedly proven to be success factors are highlighted here. It should be emphasized that the topic is generally considered important and central, but is almost always neglected.
Change requires strong leadership in both program and workstream management and requires people who actively embrace change, move forward, and in doing so, bring program staff along with them and support them through the change. In many successful CAPEX transformations, dedicated change agents are employed who focus solely on the success of the change throughout the entire program.
Communication during the change must paint a clear picture of why the change is necessary and inevitable. Above all, emphasizing the why is a key lever for getting the entire team on board with the necessity of the change. Additional status reports and regular updates to the program team provide reassurance and strengthen the feeling of involvement.
Furthermore, a clear vision must be communicated of what the future target state will look like after the CAPEX investment and what skills and processes will be necessary or required for success. This enables future operating teams to anticipate their own position in future operations and prepare for it during the transformation.
Another key element for successful operation is ensuring that the operating personnel have the necessary skills. Competence matrices provide an overview of the required skills and form the basis for the personnel training plan. In addition to these primarily person-specific skills, a functioning team structure also plays an important role. Measures to strengthen this often fall off the action list before the plant goes into operation. Nevertheless, it has been shown time and again that teams that had the opportunity to get to know each other before the start of operation and even to carry out the commissioning together functioned more quickly as a team and were thus able to utilize the planned plant capacity more quickly. Investing time and resources as early as possible is also important for building up these skills.
Timeline, investment, and conclusion
In addition to all these important organizational and content-related steps, the timeliness of the overall planning and the involvement of future plant operators are of central importance (Fig. 2). Ideally, budgeting and rough planning for the program should already be completed during the CAPEX decision. The program should ideally start before the commissioning phase. Future key user representatives should be involved as early as the definition of user requirement specifications. Future operators must be integrated during the commissioning phase at the latest to ensure the best possible learning path.
A smooth transition from the project phase to the productive phase requires planning and organizational foresight. Experience shows that the investment required for this is limited to 0.5-1% of the total CAPEX expenditure. In view of the revenues and profits usually expected from plant construction, this capital investment for a comprehensive transformation program on the way to OPEX represents a more than manageable cost factor.
Final Thoughts
Capital expenditure (CAPEX) programs for the construction or expansion of production facilities are increasingly characterized by time and resource constraints. Fast-track approaches are no longer the exception, but the rule. However, in addition to the timely handover of a fully functional plant, a number of additional factors are crucial to achieving the planned time-to-market and utilizing 100% of the planned plant capacity. Only when this has been achieved can the operator speak of true operational excellence (OPEX). Minimizing the total cost of ownership as a primary goal is achieved primarily through a transition from the CAPEX team to the future operators that is as frictionless as possible. During this crucial transition phase, the same shortcomings can be identified time and again, and these must be avoided. An accompanying transformation program is divided into three critical parts. The first part involves defining the overall scope and organizational framework. The second part implements the choreography of daily collaboration, including automated reporting and establishing a rolling planning and reporting cycle. Part three focuses on actively managing the critical path, optimizing the newly implemented processes, and rolling out the accompanying change and team-building measures.